Project Updates
Work Prior to Construction – 1/25, 1/26, and 1/29
In preparation for our February 5th start of construction, the contractor will be performing work on Imjin Parkway that will impact traffic in the area on January 25th, 26th, and 29th. Changes to the traffic flow will include closure of one of the left turn lanes from...
Weather Delays Construction Start
UPDATE (01/16/24): Start of construction is now anticipated to begin February 5, 2024. UPDATE (01/11/24): Start of construction is again temporarily delayed due to weather conditions and is presently now anticipated to begin mid January. Regular updates will be posted...
Project Start Date and Environmental Protections Begin
Work is currently underway to install temporary perimeter fencing for areas set aside as mitigation for the impacts to the Monterey Sand Gilia.The start of construction is now anticipated to be December 18, 2023.
Project Updates – September 28, 2023
Check out the project updates as of September 28, 2023.
Project Kickoff Highlights Importance of “Hands-On” Partnership for Community
As many locals recognize, Imjin Parkway serves as a major transportation corridor linking the Peninsula and Salinas Valley and provides access to several Marina neighborhood areas. The Imjin Parkway Widening & Roundabout Project will significantly improve safety...
Save the Date for the Project Kick-Off Event
Save the Date for the project kick-off event! There will be speakers, project information, and light refreshments.
Upcoming Kick-Off Event
We are planning a Kick-Off event for the last week in June. Stay tuned for additional details! Or signup on our Contact page to get notified of updates automatically.
Construction Preparations
Our contractor will start setting construction signs, potholing, and setting traffic control in mid to late-June.
First Interagency Task Force Meeting (ITF)
This is a brief description of the update, known as an excerpt.